Completed Construction

Construction is completed. Phase one of restoration includes slope regrading, jute netting, and optional hydroseeding.
View Project Map | View Construction Updates
Banner Lava Cap Road, between Red Gate Road and Elizabeth George Water Treatment Plant
- Raw Water pipeline installation complete: August 2011
- Raw water pipeline pressure tested and connection made to existing pipeline: November 2011
- Raw water pipeline installation complete: August 2011
- Treated water pipeline installed: November 2011
Overland from Madrone Forest Drive to Red Gate Road:
- Logging and stump grinding is complete on the Thomas Ranch: July 2011
- Raw water pipeline installation on Thomas Ranch completed: August 2011
- Creek crossing complete: September 2011
- Raw and treated water pipelines installed through Idaho Maryland Road connecting to existing pipelines: November 2011
- Trees and stumps removed: July 2010
- 36” raw water pipeline installation completed: July 2010
- 10” treated water pipeline installation completed: July 2010
- Treated water services installed: August 2010
- Final clean-up is completed: August 2010
- Vault construction is complete: September 2010
- Pipeline testing completed: October 2010
- Final pavement is completed: October 2010
- Phase one of restoration, soil stabilization, completed: October 2010
- Erosion control measures are in place for the winter: October 2010
Overland between Madrone Forest Drive and the airport:
- Trees and stumps removed: July 2010
- 36” raw water pipeline is installed: September 2010
- 36” raw water pipeline is tested: October 2010
- General clean-up completed: October 2010
- Final clean-up completed: October 2010
- Phase one of restoration, soil stabilization, completed: October 2010
- Erosion control measures are in place for the winter: October 2010
- Creek restoration and replanting completed: January 2011
- Additional hydroseed and erosion control measures in place: September 2011
Airport & Loma Rica Water Treatment Plant:
- Trees, brush, and stumps removed: June 2010
- 36” raw water pipeline installed along runway: June 2010
- General clean-up along pipeline route is completed: August 2010
- 36” raw water pipeline testing completed: October 2010
- Raw water pipeline installation from Lee Lane to the airport completed: August 2011
- Additional hydroseed and erosion control measures in place: September 2011
- 48” raw water pipeline is installed: October 2010
- 10” treated water pipeline is installed: November 2010
- Services and vaults have been completed: November 2010
- First lift of pavement has been laid: November 2010
- Curbs have been installed: December 2010
- Erosion control measures are in place for the winter: December 2010
- Raw water tie-in to Idaho Maryland Road installed: May 2011
- Treated water tie-in to Idaho Maryland Road installed: May 2011
- Treated water available for residential use and fire hydrants activated: June 2011
- Raw water pipeline testing completed successfully: June 2011
- Final paving of the roadway completed: July 2011
- Raw water pipeline installation from Lee Lane to the airport completed: August 2011
Idaho-Maryland Road, between Lee Lane and Banner Lava Cap Road:
- Scotch broom removed: July 2010
- Trees and stumps removed: July 2010
- 48” raw water pipeline is installed: November 2010
- First lift of pavement has been laid: November 2010
- Erosion control measures are in place for the winter: December 2010
- Curb installation completed: February 2011
- Phase one of restoration, soil stabilization, completed: February 2011
- Raw water tie-in to Lee Lane installed: May 2011
- Treated water tie-in to Lee Lane installed: May 2011
- Treated water available for residential use and fire hydrants activated: June 2011
- Raw water pipeline testing completed successfully: June 2011
- Final paving of the roadway completed: July 2011
- Curb replacement completed: August 2011
Banner Lava Cap Road, between Idaho-Maryland Road and Wings of Morning Drive:
- Scotch broom removed: July 2010
- Trees and stumps removed: July 2010
- 48” Raw water pipeline installation is completed: September 2010
- 12” treated water pipeline installation is completed: October 2010
- Pipeline testing completed: October 2010
- Phase one of restoration, soil stabilization, completed: October 2010
- Treated water tie-in at Altair Drive is completed: November 2010
- First lift of pavement has been laid: November 2010
- Curbs have been installed: December 2010
- Erosion control measures are in place for the winter: December 2010
- Raw water pipeline testing completed successfully: June 2011
- Final paving of the roadway completed: July 2011
- Curb replacement completed: August 2011
- Trees and stumps removed: May 2011
- Raw water pipeline installation completed: November 2011
Opalite Way/Snow Mtn. Flow Control/Overland:
- Logging complete: May 2011
- Raw water pipeline installation on the Overland section completed: August 2011
Red Dog Cross Road, Lola’s Echo Road, and Oak Ridge Road:
- Logging complete: May 2011
- Raw water pipeline installation on Oak Ridge Road and Lola’s Echo Road completed: August 2011